25.01.2017
Riga InternationaRiga International Airport – reconstruction of business waiting halll Airport – reconstruction of business waiting hall
Riga InternationaRiga International Airport – reconstruction of business waiting halll Airport – reconstruction of business waiting hall
“Latvijas Energoceltnieks” has commenced the reconstruction work of the existing airport`s business waiting hall into a public passenger area with the space of 824 m2
The work includes:
- Dismantling and transfer of the existing passport control area (borders) to the North terminal
- Reconstruction of the 3rd floor office premises at the North terminal into a business class waiting hall with the space of 866 m2
- Construction of new stairs between the 2nd and 3rd floors, and the extension of the elevator one floor higher
- Reconstruction of the internal engineering nets according to the new premise layout
The airport`s operation during the reconstruction work is not being interrupted, and the work is scheduled to be completed in May 2017.